Our Directors and Offshore Construction Managers have direct experience with some of the world's most complex offshore projects. Our team brings together incredible experiences to provide innovative turn-key offshore solutions.
2012
Monitoring of all offshore SPM Installation works with regards to 3x Full SPM Buoy Installations. Client liaison / advisor for all associated installation works.
2011
Electrical Cable laying (13,5Km) in Grondin Field Gabon. ROV Pre-lay surveys, as built surveys. Oceanic Installer (formerly, Dynamic Installer)
2011
3x SPM Anchor systems installation (18x Driven Piles and 18x anchor chains) Monitoring of all offshore installation works with regards to 3x Full SPM Buoy Installations
2010
FSO Hook-Up / Installation, 6x Mooring legs, 1x Riser, 1x Umbilical.
2010
Installation and Hook-Up of FPSO CAPIXABA, 9x Anchor Legs (1500m Water Depth)
2010
FPSO FRADE Floating Hose assembly and Installation (24” Double Line) Pressure Testing, commissioning of Floating Hose System.
2010
ELECTRICAL CABLE LYING (TOTAL CONGO) NORMAND INSTALLER Laying of 4x Electrical cables Jacket to Jacket, and hook up into Platforms.
2009
FDPSO AZURITE Hook up, 12x Anchor legs (Fixed spread Mooring)
2009
Floating Hose string assembly, installation, and pressure testing.
2009
Installation of 6x Driven Piles and anchor chains (184mm) and the recovery of old mooring spread.
2008
Disaster management, oil prevention and salvage of detached SALM buoy. Diving works on SALM base, closing of pipe-line valve, blanking off hard piping and air lifting of SALM base for inspection
2008
Installation and commissioning of SALM Buoy (Sakhalin Russia). SALM Repair Works (Japan) Supervising of repair works to SALM Buoy in Japan. Preparations of towing arrangement and instillation aids.
2008
Disconnection of 12-inch Riser and 9 Anchor legs. Hook up towing vessels and tow to anchorage site. Disconnection and disassembly of Floating Hose Strings.
2008
All preparations for FPSO FRADE installation, Turret Works, Towing arrangements, Installation Aids and air diving area prep works.
2007
Normand Installer Nigeria suction pile instillation (Agbami field) 12x 100-ton suction piles installed in Agbami Field Nigeria (1200m water depth)
PANMARINA develops tailored offshore solutions that work specifically for Client operations. Our flexible and collaborative approach ensures stakeholder satisfaction and reliable work delivery.